Fourth Street Stormwater Improvement Project

Project status_Complete
Project GoalRain garden diagram showing ponded water depth.
The goal is to control localized flooding and improve water quality using Low Impact Development (LID) rain gardens.
   
Project Schedule
  • Construction - the project began construction in July, 2014.
  • The projected is projected for completion in November, 2014. 
Budget
  Funded by Stormwater Utility Rates and a $1 million Ecology Grant.

   Construction Award: $1,125,307.65
  